Installation Guide for Dual-Geotextile Composite Liner

‌I. Construction Preparation‌

‌A. Subgrade Preparation‌

  1. Clear construction area of debris and sharp objects
  2. Verify subgrade meets specifications:
    • Dryness (≤15% moisture content)
    • Compaction (≥95% Proctor density)
    • Surface regularity (±10mm/3m tolerance)

‌B. Material Readiness‌

  1. Procure composite liners meeting ASTM D5994/D7007 standards
  2. Verify geosynthetic properties:
  3. Confirm roll dimensions against shop drawings

‌II. Deployment Sequence‌

‌A. Primary Geotextile Layer‌

  1. Unroll nonwoven geotextile without stretching
  2. Achieve full contact with subgrade
  3. Secure with corrosion-resistant anchors (300mm spacing)

‌B. Geomembrane Placement‌

  1. Align HDPE geomembrane over primary geotextile
  2. Maintain ≥150mm side overlaps
  3. Anchor perimeter with continuous trench backfill

‌C. Secondary Geotextile Layer‌

  1. Install protective nonwoven layer over geomembrane
  2. Apply minimal tension during placement
  3. Secure with U-pins at 1m grid intervals

‌

Installation Guide for Dual-Geotextile Composite Liner
Installation Guide for Dual-Geotextile Composite Liner

III. Seaming Procedures‌

‌A. Joint Techniques‌

MethodApplicabilityOverlap
Thermal FusionGeomembrane≥100mm
Sewn SeamsGeotextiles≥75mm
Adhesive TapeEmergency repair≥200mm

‌B. Quality Assurance‌

  1. Conduct seam integrity tests per ASTM D4437:
    • Air lance testing (200kPa)
    • Vacuum box (35kPa)
    • Ultrasonic scanning
  2. Document all test results

‌IV. Protective Measures‌

‌A. Transition Layer‌

  1. Apply 100mm sand/clay cushion layer
  2. Compact to 90% relative density

‌B. Armor System‌

  1. Install 200-300mm riprap or precast blocks
  2. Critical placement protocol:
    • Use geotextile-protected equipment
    • Limit drop height to ≤0.5m
    • Sequential installation with liner deployment

‌V. Critical Considerations‌

‌A. Environmental Controls‌

  1. Prohibit work during precipitation
  2. Achieve daily backfill coverage on GCL

‌B. Material Handling‌

  1. Enforce non-smoking zones
  2. Prevent hydrocarbon contamination

‌C. Backfilling Protocol‌

  1. Layered placement sequence:
    • Coarse sand → Graded aggregate → Rockfill
  2. Lift thickness limits:
    MaterialMax. Thickness
    Sand200mm
    Aggregate300mm
    Rockfill500mm
  3. Monitor settlement rates (<5mm/day)

‌D. Crew Composition‌

  • Certified welder (1 per 500m²)
  • Survey technician
  • Heavy equipment operator
  • General laborers (3:1 ratio)

Compliance: ASTM D5819, GRI GM19, ISO 9001:2015

Scroll to Top